scrum - How can a team decide to pick a user story for a sprint, when the Product Manager has already decided on PBI ordering? -
an exam asked: decides take user story sprint, product manager or team? correct answer team.
i understand that:
- product manager prioritizes product backlog items (pbi).
- team members select user stories sprint.
- pbis , user stories seem synonymous.
so, how can team decide pick user story sprint, when product manager has decided on pbi ordering?
it explained jessehouwing.
only team decides on selecting user story sprint team has clear understanding of it's capacity & other dependencies implementing user story. product owner prioritise pb , put his/her wish in front of team. team selects pbi can deliver. team's responsibility deliver whatever have picked sprint. team committed deliverables , po involved (chicken & pig).